May 2019 – Construction Began.
June 24th, 2019 through August 2nd, 2019 – Eifert Road storm sewer construction north of the intersection of Nichols Road and Eifert Road.
July 22nd, 2019 – Start of culvert improvements in main channel and yard restorations along Eifert Road.
August 12th, 2019 – Tentative start of Onondaga Road culvert improvement.
August 19th, 2019 – Tentative start of Nichols Road improvements.
September, 2019 – Start of driveway and road restoration.
October 15, 2019 – Substantial Completion.
November 15, 2019 – Final Completion.
*Schedule is tentative to weather and construction delays.