Project Schedule

Aurelius and Delhi Consolidated Drain Maintenance and Improvement Project Construction Map

May 2019 – Construction Began.

June 24th, 2019 through August 2nd, 2019 – Eifert Road storm sewer construction north of the intersection of Nichols Road and Eifert Road.

July 22nd, 2019 – Start of culvert improvements in main channel and yard restorations along Eifert Road.

August 12th, 2019 – Tentative start of Onondaga Road culvert improvement.

August 19th, 2019 – Tentative start of Nichols Road improvements.

September, 2019 – Start of driveway and road restoration.

October 15, 2019 – Substantial Completion.

November 15, 2019 – Final Completion.

*Schedule is tentative to weather and construction delays.

**PLEASE CONTACT US IF THERE ARE ANY CONFLICTS WITH THE SCHEDULE ABOVE OR CONSTRUCTION (MEDICAL TRANSPORTATION, OPEN HOUSES, RECEPTIONS, WEDDINGS, ETC…)

%d bloggers like this: